Bridge over Moerbrugsestraat - Oostkamp

Description 

The project involves replacing the arch bridge over Moerbrugsestraat in Oostkamp, widening the bridge over the River Brook and adapting the Moerbrugsestraat road alignment between Rivierstraat and Stationsstraat. The new arch bridge consists of two lanes for motorised traffic and a cycle path along both sides.

  • Foundation, sub- and superstructure of the bridge;
  • Adjustment of cross-section and longitudinal profile;
  • Local adaptation of overhead lines and signalling.

Willemen Construct came into being on 1 July 2018 as a result of the merger between Willemen General Contractor and the construction department of Kumpen.

 
location 

Project Details

Contractor
Moerbrugsestraat , Oostkamp, West-Vlaanderen, Belgium
Client 
Infrabel
Engineering Office 
Tuc Rail
Construction period
1 year 7 months
Start work
11-2016
End of work
06-2018